Per-agent work document — weeks 1–4

Each of the 50 agents has an explicit ticket list for the first four weeks (Phase 0 + Sprint 1 of Phase 1). Tickets are keyed to commit IDs in 04-commits.md. Where an agent's work is research / documentation / sales pipeline rather than commits, the ticket is described as a deliverable instead.

Conventions:

  • → C-NNN references a commit ID from 04-commits.md.
  • [Lead] means the agent owns the commit subject and PR.
  • [Reviewer] means the agent signs off but does not author.
  • [Pair] means the agent co-authors with another agent on a single PR.
  • Each week's tickets are scoped to fit one ~8 h workday × 5 = 40 h.

For weeks 5+ tickets, each agent will receive an end-of-week-4 update with their next sprint plan, generated from the sprint commit list and customer feedback. The plan is intended to be re-confirmed at the start of each sprint.


Engineering (roles 1–27)

Agent #1 — Chief Engineering Officer

  • Week 1
    • [Lead] → C-002 (ADR 0008 branching workflow), C-033 (update CLAUDE.md for Phase 0 final state — week-2 work, drafted week 1).
    • [Reviewer] every PR landed in weeks 1–2.
    • Deliverable: Phase 0 kickoff brief sent to all 50 agents end of week 1, day 1.
  • Week 2
    • [Lead] → C-033 finalised after C-001..C-032 land.
    • [Reviewer] every PR; arbitrate any ADR disagreements; sign off Phase 0 exit gate.
    • Deliverable: Phase 0 exit-gate review with security-reviewer + cryptographer-reviewer subagents.
  • Week 3
    • [Lead] kickoff of Phase 1 Sprint 1; review C-101..C-108 PRs.
    • Deliverable: Sprint 1 retro at end of week 4.
  • Week 4
    • [Reviewer] C-101..C-108 final PRs; Phase 1 Sprint 1 exit-gate sign-off.
    • Deliverable: Sprint 2 ticket list confirmed with VPs.

Agent #2 — VP Engineering, Backend

  • Week 1
    • [Reviewer] → C-004 (demo bypass removal), C-005 (access_token query fallback removal).
    • [Lead] backend team daily standup; track per-agent progress.
    • Deliverable: backend dependency-graph for weeks 1–4 drawn and shared.
  • Week 2
    • [Reviewer] → C-018 (circuit version lock), C-022 (zod adoption), C-025 (Postgres session store), C-026 (rate-limit).
    • Deliverable: backend agent sprint plan for sprint 1.
  • Week 3
    • [Reviewer] → C-105 (redesigned identity register).
    • Deliverable: API contract delta document shared with mobile + frontend.
  • Week 4
    • [Reviewer] → C-107 (dashboard users view), C-108 (Anchor Bank tenant seed).
    • Deliverable: sprint 1 retro within engineering org.

Agent #3 — VP Engineering, Frontend

  • Week 1
    • [Reviewer] → C-006 (dashboard SSE migration).
    • Deliverable: frontend agent sprint plan + design-system audit for sprint 1.
  • Week 2
    • [Reviewer] no anchor commits this week from frontend; track polish items.
    • Deliverable: design tokens repo audited; demo-friendly theme prepared.
  • Week 3
    • [Reviewer] → C-107 (users view).
    • Deliverable: Anchor Bank dashboard mock review with Role 32.
  • Week 4
    • [Reviewer] → polish PRs for users view, audit-integrity prep.
    • Deliverable: kiosk web app spec finalised with Role 15.

Agent #4 — VP Engineering, Mobile

  • Week 1
    • [Lead] → C-102 (ADR 0014 android-only).
    • Deliverable: mobile-team kickoff; rapidsnark toolchain plan with Role 11; device-fleet procurement spec.
  • Week 2
    • [Reviewer] → C-103 (ADR 0015 rapidsnark vs WebView).
    • Deliverable: device-support matrix v0; physical test phones ordered (Pixel 7, S22, Redmi Note 13, OnePlus 11, Realme GT, Moto Edge).
  • Week 3
    • [Reviewer] → C-101 (bootstrap mobile/ subtree), C-104 (rapidsnark JNI POC).
    • Deliverable: R307 sensor procurement spec; two R307 units ordered.
  • Week 4
    • [Reviewer] → C-104 final, weekly mobile sync, planning of Sprint 2 mobile commits.
    • Deliverable: mobile sprint 1 retro.

Agent #5 — VP Engineering, Infrastructure / SRE

  • Week 1
    • [Lead] → CI pipeline review; mirror pre-commit hook in CI (C-001 follow-on).
    • [Reviewer] → C-001 (pre-commit hook).
    • Deliverable: observability inventory; metric pipeline plan.
  • Week 2
    • [Reviewer] → C-015 (anchor-job cron), C-032 (CVE monitor).
    • Deliverable: deploy pipeline audit; secrets rotation calendar.
  • Week 3
    • [Lead] → device-fleet CI integration plan (mobile instrumented tests against a physical-device farm).
    • Deliverable: SLA monitoring stack provisioned in test env.
  • Week 4
    • [Lead] → load-test infrastructure scaffolding (C-191 precursor).
    • Deliverable: incident-response runbook v1.

Agent #6 — Senior Backend Engineer (verifier)

  • Week 1
    • [Lead] → C-004 (remove demo bypass from submitProof).
    • [Pair with Role 23] → write tests/proof-pairing.test.ts cases first.
  • Week 2
    • [Lead] → C-022 (zod validators on identity + zkp routes), C-023 (zod ADR).
    • [Reviewer] → C-018 (circuit version pin).
  • Week 3
    • [Lead] → C-105 (redesigned /v1/identity/register with attestation), C-106 (ADR 0016 Play Integrity acceptance).
  • Week 4
    • [Lead] → C-148 prep work (week 5 anchor: harden /v1/zkp/verify); spike the proof-verification + audit-row enrichment design.
    • Deliverable: proof-verification design doc with failure-mode matrix.

Agent #7 — Senior Backend Engineer (multi-tenancy + API keys)

  • Week 1
    • [Lead] → C-005 (remove access_token query fallback), C-007 (cross-tenant rejection test matrix).
  • Week 2
    • [Lead] → C-025 (Postgres-backed session store), C-026 (rate-limit middleware), C-027 (CORS hardening).
  • Week 3
    • [Lead] → C-108 (anchor_bank tenant seed in test env).
    • [Pair with Role 14] → users view API surface.
  • Week 4
    • [Lead] → tenant feature-flag service refactor (precursor to workforce-mode in C-189).
    • Deliverable: tenant config schema documented in docs/operations/tenant-config.md.

Agent #8 — Senior Backend Engineer (audit + blockchain)

  • Week 1
    • [Pair with Role 11] → C-009 (ADR 0010 hash chain), C-011 (audit_events.previous_hash + event_hash columns).
  • Week 2
    • [Lead] → C-012 (audit chain implementation), C-013 (route all writes through appendAuditEvent), C-014 (audit-integrity endpoint).
    • [Pair with Role 25] → C-015 (anchor cron) and C-016 (AuditAnchor contract).
  • Week 3
    • [Lead] → audit-chain enforcement in test env, backfill migration prep.
  • Week 4
    • [Lead] → migration dry-run on staging; observability for audit-write lag.
    • Deliverable: hash-chain runbook for on-call.

Agent #9 — Senior Backend Engineer (admin + reporting)

  • Week 1
    • [Pair with Role 23] → C-007 (cross-tenant test additions for admin endpoints).
  • Week 2
    • [Lead] → C-024 (/api/admin/dump-users for breach-sim demo).
    • [Reviewer] → C-014 (audit-integrity endpoint).
  • Week 3
    • [Lead] → admin compliance-export CSV scaffolding (precursor to weeks 5+ work).
  • Week 4
    • [Lead] → admin endpoint audit-row coverage tests.
    • Deliverable: admin endpoint inventory in docs/api_contract.md.

Agent #10 — Senior Backend Engineer (compliance integrations)

  • Week 1
    • [Lead] → SAML / OIDC adapter inventory review; identify which target bank uses which.
  • Week 2
    • [Pair with Role 37] → consent-capture data model spec for RBI Digital Lending compliance.
  • Week 3
    • [Lead] → consent flow schema PR (precursor; not yet wired to a route).
  • Week 4
    • [Lead] → Anchor Bank webhook receiver smoke test scaffolding (precursor to C-125).
    • Deliverable: integration-architecture template for partner banks.

Agent #11 — Senior Cryptography Engineer (circuit + prover)

  • Week 1
    • [Lead] → C-008 (ADR 0009 QR proof pairing protocol), C-009 (ADR 0010 audit hash chain spec).
  • Week 2
    • [Lead] → C-018 (circuit version pin v1.1), C-019 (ADR 0012 version pinning + upgrade procedure).
    • [Reviewer] → C-012 (audit chain implementation), C-016 (AuditAnchor contract).
  • Week 3
    • [Lead] → C-103 (ADR 0015 rapidsnark vs WebView).
    • [Reviewer] → C-104 (rapidsnark JNI POC).
  • Week 4
    • [Lead] → trusted-setup ceremony v1.2 invitation drafts + contributor recruitment (precursor to C-169).
    • Deliverable: trusted-setup runbook draft.

Agent #12 — Senior Cryptography Engineer (key management + HSM)

  • Week 1
    • [Lead] → key-inventory document; identify all production keys (JWT, session, admin, blockchain, attestation).
  • Week 2
    • [Lead] → C-028 (JWT migrate to RS256 + JWKS endpoint).
    • [Pair with Role 6] → JWKS in zod validator path.
  • Week 3
    • [Lead] → StrongBox attestation chain validation library (precursor to mobile attestation path).
  • Week 4
    • [Lead] → HSM evaluation: AWS CloudHSM vs YubiHSM2 trade-off paper.
    • Deliverable: HSM ADR draft.

Agent #13 — Mid Cryptography Engineer (Poseidon + hash chain)

  • Week 1
    • [Pair with Role 11] → Poseidon test vectors matched against circomlibjs reference; landed as tests/poseidon-vectors.test.ts.
  • Week 2
    • [Lead] → hash-chain primitive helpers landed in src/services/audit.ts (companion to C-012).
  • Week 3
    • [Lead] → external cryptographer engagement letter coordinated with Role 27.
  • Week 4
    • [Lead] → cryptographer-reviewer subagent rules expanded (companion to C-030).
    • Deliverable: cryptanalysis-readiness checklist.

Agent #14 — Senior Frontend Engineer (dashboard)

  • Week 1
    • [Lead] → C-006 (dashboard EventSource migration to cookie + CSRF).
  • Week 2
    • [Reviewer] → C-024 prep work; design system audit follow-ups.
  • Week 3
    • [Lead] → C-107 (users view, allowed-columns enforcement).
  • Week 4
    • [Lead] → audit-integrity dashboard view (companion to C-123, week 5 anchor).
    • Deliverable: dashboard storybook coverage for new components.

Agent #15 — Senior Frontend Engineer (developer console + kiosk)

  • Week 1
    • [Reviewer] → C-005 (console SSE auth migration; backend lead is Role 7).
  • Week 2
    • [Reviewer] → C-006; spec for kiosk web app drafted.
  • Week 3
    • [Lead] → kiosk web app skeleton (precursor to C-147).
  • Week 4
    • [Lead] → kiosk SSE consumer + QR generator (continues into C-147 week 7).
    • Deliverable: kiosk demo-day UX run-through with Role 32.

Agent #16 — Mid Frontend Engineer (docs + marketing)

  • Week 1
    • [Lead] → docs site updates: new ADRs surfaced, security-findings link added.
  • Week 2
    • [Lead] → docs site search tuning; landing page CTAs refreshed.
  • Week 3
    • [Lead] → pain-points page on the public docs site (docs/why-zeroauth/bfsi.md).
  • Week 4
    • [Lead] → developer onboarding page revamp (precursor to SDK launch in week 17).
    • Deliverable: docs-site analytics dashboard live.

Agent #17 — Senior Android Engineer (prover core + biometric prompt)

  • Week 1
    • [Pair with Role 4] → C-101 (mobile subtree bootstrap).
  • Week 2
    • [Lead] → C-104 (rapidsnark JNI POC).
  • Week 3
    • [Lead] → mobile prover module skeleton; instrumented test framework set up.
  • Week 4
    • [Lead] → enrollment flow spike with CameraX (precursor to C-143).
    • Deliverable: prover-latency measurement on Pixel 7 against fixed witness.

Agent #18 — Senior Android Engineer (R307 + BiometricPrompt fallback)

  • Week 1
    • [Lead] → R307 datasheet review; USB-OTG enumeration spike outside the app.
  • Week 2
    • [Lead] → R307 driver design doc; USB-Serial library selection (ADR 0017 candidate).
  • Week 3
    • [Lead] → R307 driver skeleton module added to mobile/sensors/r307/.
  • Week 4
    • [Lead] → BiometricPrompt fallback path skeleton; capability-detection helper.
    • Deliverable: R307 reliability test plan.

Agent #19 — Mid Android Engineer (UX + flows)

  • Week 1
    • [Lead] → enrollment flow Compose screens mockup; navigation graph drafted.
  • Week 2
    • [Lead] → login flow Compose screens; QR-scan permission flow.
  • Week 3
    • [Lead] → in-app QR scanner skeleton.
  • Week 4
    • [Lead] → error-state screens (capture failure, network failure, expired session).
    • Deliverable: error-state coverage matrix.

Agent #20 — Senior IoT Engineer (kiosk bridge)

  • Week 1
    • [Lead] → IoT bridge runbook review (existing docs/operations/demo-runbook.md).
  • Week 2
    • [Lead] → bridge SSE back-channel hardening; reconnect strategy documented.
  • Week 3
    • [Lead] → bridge audit-event reconciliation with server (cross-check).
  • Week 4
    • [Lead] → bridge 24-hour burn-in test on a staged kiosk.
    • Deliverable: bridge resilience test report.

Agent #21 — Senior DevOps / SRE Engineer

  • Week 1
    • [Pair with Role 22] → C-001 (pre-commit hook + CI mirror).
  • Week 2
    • [Lead] → C-015 (anchor-job cron with CronCreate-managed schedule).
  • Week 3
    • [Lead] → metric dashboards: verifier latency, audit-write lag, anchor lag.
  • Week 4
    • [Lead] → physical-device-farm CI runner; instrumented test integration.
    • Deliverable: SRE runbook for Phase 0 exit-state alerting.

Agent #22 — Mid DevOps Engineer (CI/CD + observability)

  • Week 1
    • [Lead] → C-001 (pre-commit hook implementation + tests).
  • Week 2
    • [Lead] → C-032 (CVE monitor workflow).
    • [Pair with Role 21] → metric pipeline scaffolding.
  • Week 3
    • [Lead] → eslint rule additions: ban direct audit_events INSERT, ban Co-Authored-By: Claude in commit messages (commit-msg hook).
  • Week 4
    • [Lead] → CI matrix audit: assert no --no-verify paths in workflows; assert no shell-script cat of secrets.
    • Deliverable: CI uptime + flakiness report.

Agent #23 — Senior QA / SDET

  • Week 1
    • [Lead] → C-003 (schema-purity test), C-007 (tenant-isolation matrix), C-021 (biometric-rejection test).
  • Week 2
    • [Lead] → C-126 prep (sprint 2 anchor) + C-127 (audit-coverage test scaffolding).
  • Week 3
    • [Lead] → end-to-end Playwright suite scaffolding (precursor to C-192).
  • Week 4
    • [Lead] → e2e test for enrollment + login path against test env.
    • Deliverable: QA risk register for the Anchor Bank demo.

Agent #24 — Mid QA Engineer (regression + manual + device fleet)

  • Week 1
    • [Lead] → device-fleet manual-test plan for tier-1 SKUs.
  • Week 2
    • [Lead] → regression checklist for Phase 0 exit (run all 50 existing tests on staging).
  • Week 3
    • [Lead] → manual smoke test of enrollment flow on Pixel 7 emulator (early version).
  • Week 4
    • [Lead] → bug-triage queue audited; SLA dashboard set up.
    • Deliverable: device-test matrix v1.

Agent #25 — Senior Blockchain Engineer

  • Week 1
    • [Lead] → C-010 (ADR 0011 on-chain anchor cadence).
  • Week 2
    • [Lead] → C-016 (AuditAnchor contract on Base Sepolia), C-020 (redeploy Groth16Verifier at v1.1).
  • Week 3
    • [Lead] → contract-test harness expansion; deployment-script idempotence.
  • Week 4
    • [Lead] → mainnet-readiness checklist drafted; bytecode-equivalence verification documented.
    • Deliverable: contract risk register.

Agent #26 — Senior Security Engineer (red team + AppSec)

  • Week 1
    • [Lead] → C-031 (audit-findings doc) + tracking the 21 findings across the team.
  • Week 2
    • [Lead] → C-029 (security-reviewer subagent hooks expansion).
  • Week 3
    • [Reviewer] → all PRs touching auth, crypto, tenant boundaries.
  • Week 4
    • [Lead] → internal red-team exercise plan v1; OWASP top-10 evidence audit.
    • Deliverable: bug-bounty platform vendor evaluation (phase 3 deliverable; pre-work).

Agent #27 — Senior Security Engineer (cryptanalysis + circuit review)

  • Week 1
    • [Reviewer] → C-008, C-009 (the QR pairing and hash-chain ADRs).
  • Week 2
    • [Lead] → C-030 (cryptographer-reviewer subagent hooks expansion).
  • Week 3
    • [Reviewer] → C-104 (rapidsnark JNI POC).
  • Week 4
    • [Lead] → external cryptographer engagement secured (signed SoW); coordinated with Role 12.
    • Deliverable: trusted-setup ceremony date confirmed with 6 contributors.

Product & Design (roles 28–35)

Agent #28 — Chief Product Officer

  • Week 1
    • Deliverable: Anchor Bank demo prioritisation matrix; final list of 6 target banks confirmed with Role 42.
  • Week 2
    • Deliverable: pain-point document 01-pain-points.md reviewed; updates with internal feedback.
  • Week 3
    • Deliverable: bank-PM Role 29 working session — what the CRO at HDFC will say in Q&A.
  • Week 4
    • Deliverable: demo runbook draft sign-off (precursor to C-190).

Agent #29 — Senior PM (BFSI)

  • Week 1
    • Deliverable: per-bank intel pack (HDFC, ICICI, Axis, SBI YONO, IDFC First, RBL) — CISO names, recent breach/audit posture, RBI inspection cycle.
  • Week 2
    • Deliverable: bank-CISO Q&A bank (02-bank-demo.md Q&A section expanded with bank-specific lines).
  • Week 3
    • Deliverable: pain-point doc v1.1 with quantified numbers validated against 2 industry analysts.
  • Week 4
    • Deliverable: demo invitation drafts for each of the 6 banks; legal review of LoI template.

Agent #30 — PM (Healthcare)

  • Week 1
    • Deliverable: ABDM (Ayushman Bharat Digital Mission) integration overview; HRP (Health Record Provider) interface review.
  • Week 2
    • Deliverable: healthcare pain-points draft v0 (deferred to Phase 2 but pre-work).
  • Week 3
    • Deliverable: target healthcare partners shortlisted (Apollo, Manipal, Fortis).
  • Week 4
    • Deliverable: healthcare demo storyboard draft.

Agent #31 — PM (Developer Experience)

  • Week 1
    • Deliverable: SDK strategy doc (precursor to Node SDK in Phase 2); language priority confirmed.
  • Week 2
    • Deliverable: developer onboarding flow audit; time-to-first-API-call measurement on current docs.
  • Week 3
    • Deliverable: SDK API surface spec for Node SDK v1.
  • Week 4
    • Deliverable: developer-feedback synthesis from existing console signups (anonymised).

Agent #32 — Senior Designer (Dashboard UX)

  • Week 1
    • Deliverable: design system audit; demo-friendly theme palette explored.
  • Week 2
    • Deliverable: users view mock with allowed-columns-only treatment.
  • Week 3
    • Deliverable: audit-integrity view mock; on-chain anchor link treatment.
  • Week 4
    • Deliverable: kiosk web app visual design (works for Scene 2).

Agent #33 — Designer (Mobile UX)

  • Week 1
    • Deliverable: enrollment flow Figma file v1 (CameraX face, biometric prompt, success state).
  • Week 2
    • Deliverable: login flow Figma file (QR scan, biometric confirm, redirect).
  • Week 3
    • Deliverable: transaction-confirmation sheet Figma file with Indian numbering format.
  • Week 4
    • Deliverable: error-state coverage in Figma; usability test plan.

Agent #34 — Technical Writer (developer docs)

  • Week 1
    • Deliverable: docs/api_contract.md review for accuracy against current state.
  • Week 2
    • Deliverable: docs/error_codes.md audit; map every machine-readable error to a remediation.
  • Week 3
    • Deliverable: integration guide skeleton for a target bank's net-banking team.
  • Week 4
    • Deliverable: kiosk integration docs page.
  • Week 1
    • Deliverable: docs/security/audit-findings.md collaboration with Role 26.
  • Week 2
    • Deliverable: threat-model docs/threat_model.md updated for hash chain + on-chain anchor (companion to C-017).
  • Week 3
    • Deliverable: DPDP §2(t) legal memo draft (precursor to a counsel review in week 9).
  • Week 4
    • Deliverable: anchor-bank demo runbook outline (precursor to C-190).

Compliance & Risk (roles 36–41)

Agent #36 — Chief Compliance Officer

  • Week 1
    • Deliverable: compliance roadmap calendar (SOC 2 + ISO 27001 + DPDP + RBI sandbox) v1.
  • Week 2
    • Deliverable: SOC 2 auditor shortlist (Sequence, Strike Graph, A-LIGN, Vanta-partnered).
  • Week 3
    • Deliverable: SOC 2 scope memo drafted.
  • Week 4
    • Deliverable: ISO 27001 ISMS scope memo drafted.

Agent #37 — Senior Compliance Lead (DPDP + RBI)

  • Week 1
    • Deliverable: DPDP §2(t) external counsel engagement scoped.
  • Week 2
    • Deliverable: RBI Master Direction on IT Governance §6.4 compliance matrix v0.
  • Week 3
    • Deliverable: RBI Digital Lending Guidelines mapping document.
  • Week 4
    • Deliverable: DPDP §8 (data breach reporting) playbook v0.

Agent #38 — Senior Compliance Lead (SOC 2 + ISO 27001)

  • Week 1
    • Deliverable: SOC 2 Type I scope draft; control identification (~120 controls).
  • Week 2
    • Deliverable: ISO 27001 Annex A control mapping draft.
  • Week 3
    • Deliverable: evidence collector inventory (commits, PRs, access reviews, vendor reviews).
  • Week 4
    • Deliverable: control-narrative writing started for 30 controls.

Agent #39 — Senior Privacy Engineer

  • Week 1
    • Deliverable: data inventory v1 — every data element processed, classified, sensitivity-tagged.
  • Week 2
    • Deliverable: privacy impact assessment template; first PIA against current state.
  • Week 3
    • Deliverable: data-retention policy v0 with per-table retention rules.
  • Week 4
    • Deliverable: privacy section of threat model updated.

Agent #40 — Risk & Audit Lead

  • Week 1
    • Deliverable: risk register v1 (the 10-item enterprise risk register).
  • Week 2
    • Deliverable: incident response runbook v0; severity classification grid.
  • Week 3
    • Deliverable: audit-log integrity continuous-verification design.
  • Week 4
    • Deliverable: quarterly risk review cadence proposed.

Agent #41 — Data Protection Officer

  • Week 1
    • Deliverable: DPO registration prep with Data Protection Board.
  • Week 2
    • Deliverable: data-subject request handling SOP.
  • Week 3
    • Deliverable: breach notification SOP.
  • Week 4
    • Deliverable: data-localisation audit on the current stack (Indian VPS, region locked).

Sales, BD, GTM (roles 42–49)

Agent #42 — Chief Revenue Officer

  • Week 1
    • Deliverable: pricing model v1 (per-seat per-month for BFSI, with tiered usage); MSA template scoped.
  • Week 2
    • Deliverable: design partner program v1 (terms, IP rights, exclusivity windows).
  • Week 3
    • Deliverable: pilot LoI template legally reviewed.
  • Week 4
    • Deliverable: pipeline tracking spreadsheet across 6 banks.

Agent #43 — Enterprise AE (BFSI North)

  • Week 1
    • Deliverable: warm intros mapped for HDFC, ICICI, Axis, Yes, IDFC First, RBL CISOs/CTOs/CIOs.
  • Week 2
    • Deliverable: outreach sequence v1; 5 first emails sent.
  • Week 3
    • Deliverable: first 2 introductory calls booked.
  • Week 4
    • Deliverable: first demo slot booked (target: week 13 — first week of Phase 2).

Agent #44 — Enterprise AE (BFSI South + PSBs)

  • Week 1
    • Deliverable: SBI YONO + Federal + KVB + KB + Indian Bank + PSB outreach prep.
  • Week 2
    • Deliverable: outreach sequence v1; first 5 emails sent.
  • Week 3
    • Deliverable: first 2 calls booked.
  • Week 4
    • Deliverable: first demo slot booked.

Agent #45 — Solutions Architect (pre-sales)

  • Week 1
    • Deliverable: integration architecture template; 3 reference architectures (net-banking, branch teller, transaction step-up).
  • Week 2
    • Deliverable: demo equipment kit specced (laptop, Pixel 7, Samsung S22, R307 sensor, OTG cable, projection adapters).
  • Week 3
    • Deliverable: demo dry-run with engineering team — Scenes 1 and 2 only.
  • Week 4
    • Deliverable: SOW template for integration phase.

Agent #46 — Customer Success Manager (BFSI)

  • Week 1
    • Deliverable: pilot lifecycle template (kickoff → integration → soft launch → review → expansion).
  • Week 2
    • Deliverable: bank-specific risk tracker.
  • Week 3
    • Deliverable: quarterly business review template.
  • Week 4
    • Deliverable: support escalation matrix.

Agent #47 — Developer Advocate

  • Week 1
    • Deliverable: conference calendar v1 (3 target conferences in phase 1).
  • Week 2
    • Deliverable: first technical blog post drafted ("why we replaced credential storage with commitments").
  • Week 3
    • Deliverable: first blog post published.
  • Week 4
    • Deliverable: first conference talk abstract submitted.

Agent #48 — Marketing Lead

  • Week 1
    • Deliverable: brand audit; press list for tier-1 BFSI tech press.
  • Week 2
    • Deliverable: BFSI landing page draft.
  • Week 3
    • Deliverable: first press conversation booked.
  • Week 4
    • Deliverable: marketing funnel v1 wired up (analytics).

Agent #49 — Content / Demand-Gen Lead

  • Week 1
    • Deliverable: content calendar v1 (12 pieces in phase 1).
  • Week 2
    • Deliverable: first 2 pieces in production.
  • Week 3
    • Deliverable: SEO strategy v1; first 5 target keywords identified.
  • Week 4
    • Deliverable: webinar program v0.

Operations (role 50)

Agent #50 — Operations / Office Manager

  • Week 1
    • Deliverable: vendor inventory (cloud, SaaS, hardware); contract dates tracked.
  • Week 2
    • Deliverable: monthly close calendar; payroll calendar.
  • Week 3
    • Deliverable: travel + procurement SOP for the device fleet and R307 sensors.
  • Week 4
    • Deliverable: HR ops calendar (performance reviews timed to phase boundaries).

Cross-team handoffs in weeks 1–4

HandoffFromToWhenArtefact
Schema purity test allowlistRole 23Role 6, 7W1tests/schema-purity.test.ts
Demo bypass removal sign-offRole 6Role 26 + Role 27W1PR review
Hash-chain specRole 11Role 8 + Role 13W1ADR 0010
On-chain anchor specRole 25Role 8 + Role 21W1ADR 0011
Pre-commit hookRole 22Role 1 + all agentsW1.husky/pre-commit
Cross-tenant test matrixRole 23Role 7 + Role 9W1tests/tenant-isolation.test.ts
Zod adoption ADRRole 6Role 1W2ADR 0013
RS256 JWT migrationRole 12Role 6 + Role 7W2C-028 PR
AuditAnchor contract on Base SepoliaRole 25Role 8 + Role 21W2contracts/deployed-addresses.json
Audit-findings tracking docRole 26Role 1W2docs/security/audit-findings.md
Mobile subtree bootstrapRole 17 + Role 4Role 5 + Role 21W3mobile/ PRs
rapidsnark JNI POCRole 17Role 11 + Role 27W3C-104 PR
Redesigned identity registerRole 6Role 17 (mobile client)W3C-105 PR
Anchor Bank tenant seedRole 7Role 14 + Role 45W3C-108 PR
Users view renderingRole 14Role 32 (UX) + Role 26 (sec)W3C-107 PR
Pain-point doc v1.1Role 29Role 28 + Role 42W301-pain-points.md
Demo invitation draftsRole 29Role 43 + Role 44W4invitation templates
Demo dry runRole 45Role 1 + Role 28 + Role 42W4dry-run recording
Integration architecture templateRole 45Role 43 + Role 44W4reference architecture doc
First demo slot bookedRole 43 or 44Role 1 + Role 28 + Role 42W4calendar invite

Friday-cadence status format (each agent posts at end of week)

Every agent posts a 4-line update in the team channel each Friday by 18:00 IST:

Agent #N — <role title>
Tickets closed: <commit IDs or deliverable refs>
Tickets in-flight: <commit IDs>
Blocker / ask: <one sentence or "none">
Next-week focus: <one sentence>

Role 1 + the line VPs (2, 3, 4, 5, 28, 36, 42) read every Friday update and respond by Monday standup.


LAST_UPDATED: 2026-05-27